Monday, March 30 2015

Although the builder is contractually obliged to return to the residence within a minimum 120 days to rectify any defects observed after (or during) Practical Completion, your builder is also responsible to rectify defects and incomplete work for 6 years from the date of practical completion. If your builder dies or becomes insolvent the building work is insured under a home owner warranty or building warranty and your insurer will take over.

Posted by: shs admin AT 05:31 pm   |  Permalink   |  Email

Time limits on complaints for Building Work.

There are essentailly two reasons why you would have a building complaint. They are:

  • You have been adversely affected by building work (this can be a builder you hired or even one that your neighbours have engaged).
  • You have a contract dispute.

As set out in the Building Services (complaint Resolution and Administration Act 2011

Building Services Complaint:

A building service complaint must be made within 6 years after the completion of the regulated building service to which the complaint relates. This means 6 years from Pratccial Completion. It is interesting to note that a Building Services complaint may be made by sebsequent owners for a period of 6 years after PCI.

An example of a Building Services complaint is if the neighbours engaged a builder to construct a new home and the stormwater drainage is affecting your property.

Another example is if you hired a builder to install some new windows and they have begun to crack within 6 years.

If the builder attends to fix something, you get another 6 years waranty 


A Breach of Contract:

You have 3 years to lodge a claim for a contract dispute.

An example may be that you requested a specific brand of tile and it was not installed or the builder did not finish the home building work on time.