Skip to main content

0401 953 226

Registered Building Inspector

  • Fully inclusive
  • Comprehensive Reporting 
  • Registered Builder
  • Qualified, reliable reporting

Pre Purchase Inspections and Practical Completion Reports Perth

W.A. Building Service Provider License # 14348

Email: christian@shsbuildingconsultants.com.au

0401 953 226

Your investment is in safe hands with SHS Building Consultants.

Friday, August 28 2015

Efflorescence

What is it?

Bricks and concrete are made of materials from the earth which contains salts and minerals. Efflorescence typically occurs during the initial cure of a cement or brickwork product. It is common on masonry construction, particularly brick, when water moving through a structure brings salts which are already in the brick to the surface. As the water evaporates, it leaves the salt behind, which forms a white, fluffy deposit, that can normally be brushed off. 

What can efflorescence indicate?

The presence of efflorescence can indicate a water leak or damp issues.

Posted by: SHS Admin AT 05:27 pm   |  Permalink   |  Email

Time limits on complaints for Building Work.

There are essentailly two reasons why you would have a building complaint. They are:

  • You have been adversely affected by building work (this can be a builder you hired or even one that your neighbours have engaged).
  • You have a contract dispute.

As set out in the Building Services (complaint Resolution and Administration Act 2011

Building Services Complaint:

A building service complaint must be made within 6 years after the completion of the regulated building service to which the complaint relates. This means 6 years from Pratccial Completion. It is interesting to note that a Building Services complaint may be made by sebsequent owners for a period of 6 years after PCI.

An example of a Building Services complaint is if the neighbours engaged a builder to construct a new home and the stormwater drainage is affecting your property.

Another example is if you hired a builder to install some new windows and they have begun to crack within 6 years.

If the builder attends to fix something, you get another 6 years waranty 


A Breach of Contract:

You have 3 years to lodge a claim for a contract dispute.

An example may be that you requested a specific brand of tile and it was not installed or the builder did not finish the home building work on time.

0401 953 226

We undertake Building Prepurchase Inspections to all areas in Perth, Western Australia 

  • Building and Pest
  • Prepurchase
  • Structural
  • Comprehensive